Saturday, August 21, 2010

Aug 20 B Building


The guys are working on the entry deck of A Building, framing visible here, it will be used for access to the first floor and will support the scaffold on this side of the building to provide access to the second floor.




We had planned to move quickly to A building last week but Fitz decided to spend more time on B Building, applying the roof felt and tacking on the purlins (waiting on arrival of 8" purlin screws). Then completing the interior walls of both floors so the electricians, plumbers and roofing crews can start next week when he moves the carpentry/panel crew to A building. It's our goal to complete the A building structure in 5 days starting on Monday. I'll post daily so we have a record of this attempt.
Wish us good weather!

No comments:

Post a Comment