Monday, July 12, 2010
Thursday, July 8, 2010
Tuesday, July 6, 2010
July 1 & 2 Trailer woes
Our 20' flat rack was MIA; when we found the rack and driver he was stuck about 1/2mile down the road from Concordia, claimed the lumber was loaded incorrectly with too much weight in the back end and he was unable to make the final hill to the property. He agreed to back it down the hill to a flat lot but then left it at a steep angle on off the road. Bad for us. Not our property, and we're unable to unload this without risk of losing the load or worse, someone getting hurt. Our guys made those braces to stabilize the load.
Thanks to Lucien, Alex and Segundo, who put in a 12 hour day including a concrete pour. Amazing.
click on any image to enlarge
July 1 Pouring again
Pour your own - June 30, 2010
No concrete available this week to pour our columns so our new Carpentry Contractor John Fitzgerald (Fitz) brought over his mixer, sand, gravel, sand and cement and the guys batched it themselves. Thanks to our regular crew, Fitz's crew, four wonderful young guys from our Maho Bay 4hr worker program and lots of buckets the columns are poured on building 1 and we're still ahead of schedule.
Friday, June 25, 2010
Forming the Columns - Rebar and Boxes
For all footings over 3 ft tall we place the stirrups 6" apart for the lowest 25% of the column height, then 8" apart for the middle 50% then 6" apart for the upper 25%. We use #5 rebar. The lumber is untreated, termite food, so when we're finished with it we'll take the 2x4 pieces not covered in concrete to our Maho Art Center to use in the Clay Studio wood burning kiln.
Pouring Footings
Geoff arrives (the shirtless one) with his son and pump truck. He's a terrific guy to work with. Always shows up when scheduled and works so hard, he keeps the whole crew on their toes (they're on their toes anyway but if they weren't..). It's getting tough to get concrete on St. John these days. Majestic Construction is the only show on island and they can't seem to get material here. They would only give us 9 yards ($265 per yard plus pump truck) when we needed 12. We'll have to pour the 10 12x12 boardwalk footings and EcoStudio deck footings when we pour the columns next week. Our Loft Duplex and Deluxe Studio units are in the background.
click on any image to enlarge