Dan has arrived from Maho with the recycled glass countertop,
making the final cuts before installation.
Bedroom area of nearly completed eco-studio waiting for furnishing to be installed next week.
Andrew working on final unit floor tiles. Steve and Chris will come in to complete the electric when Andrew finishes up later today, Sunday, Nov 28.
Edward helping out Andrew with the thinset.
Jason and John putting finishing touches on the porch railings.
Lennox installing the HardiBacker board which provides support for the floor tiles.
Jay is painting the pocket doors. These house the sliding glass and screen doors.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment