Friday, June 25, 2010
Forming the Columns - Rebar and Boxes
For all footings over 3 ft tall we place the stirrups 6" apart for the lowest 25% of the column height, then 8" apart for the middle 50% then 6" apart for the upper 25%. We use #5 rebar. The lumber is untreated, termite food, so when we're finished with it we'll take the 2x4 pieces not covered in concrete to our Maho Art Center to use in the Clay Studio wood burning kiln.
Pouring Footings
Geoff arrives (the shirtless one) with his son and pump truck. He's a terrific guy to work with. Always shows up when scheduled and works so hard, he keeps the whole crew on their toes (they're on their toes anyway but if they weren't..). It's getting tough to get concrete on St. John these days. Majestic Construction is the only show on island and they can't seem to get material here. They would only give us 9 yards ($265 per yard plus pump truck) when we needed 12. We'll have to pour the 10 12x12 boardwalk footings and EcoStudio deck footings when we pour the columns next week. Our Loft Duplex and Deluxe Studio units are in the background.
click on any image to enlarge
Thursday, June 17, 2010
Tuesday, June 15, 2010
The rebar has arrived
Monday, June 14, 2010
Materials & labor update
While the site work continues Margaret, Lyn, Maggie & Glen have been soliciting and reviewing competitive bids on all material orders over $2500.00, and are evaluating written bids received in response to our advertisement for same on carpentry, electric, plumbing, roofing, tiling and painting services.
Materials include HardiPlank Siding, Tekfoil, Tyvek, Homosote, Screws, Simpson brackets, Lumber, Plywood, Energy Star Rated Impact Resistent Windows and Doors, Energy Star Rated Metal Roofing, PV grid tie systems and Solar Hot Water systems.
Glen has signed off on the EcoPanels final shop drawings. They have started production.
Materials include HardiPlank Siding, Tekfoil, Tyvek, Homosote, Screws, Simpson brackets, Lumber, Plywood, Energy Star Rated Impact Resistent Windows and Doors, Energy Star Rated Metal Roofing, PV grid tie systems and Solar Hot Water systems.
Glen has signed off on the EcoPanels final shop drawings. They have started production.
Studio footings ready for steel - boardwalk underway
The footing boxes were completed on Thursday. Six 3x3x(min 18") and three 2x2x12" for each studio building plus two 2x2x12" for the decks. We had planned to install the #5 rebar on Thursday and Friday but ran into delays from local supplier MSI, it was promised for Thursday morning but not cut and bent until Friday and Monday and we won't receive it until tomorrow, Tuesday. If all goes well we'll tie the steel on Tues - Thurs, have a cushion day on Friday (will work on the boardwalk if we don't need it) and pour on Monday next week.
So the guys have moved onto the boardwalk. We looked at making the approach to these units a wheelchair accessible ramp but with the elevation change it would be so long it would be very expensive and would require cutting way too much vegetation. The original boardwalk design started out with a 10x10 deck, seen here.
click image to enlarge
While that would be helpful for storing material during construction it was giving us a considerable elevation to change in a short distance to the studio pod deck, required cutting the large lower branches of a terrific turpentine tree (reducing the shade) and it was too large, inconsistent with the upper property boardwalk entrance and the entry to phase 1, visible across and just down the road respectively. So we reduced the size to same as phase 1, with a 6x6 entry deck and steps dropping down immediately so it drops under the canopy and meanders nicely to the studios. We'll build a temporary sliding deck for transporting material to the upper pod and store it on the deck there.
click on image to enlarge
Friday, June 4, 2010
View from Phase 2 site
Footing boxes in situ
Subscribe to:
Posts (Atom)